Southgates Plans Revealed

The latest redevelopment of the Southgates roundabout has started.

The pictures below are still officially a 'design proposal' but show the basic ideas that the Highways team want to introduce.

The entrances from Hardwick Road and Nar Ouse Way will be widened and have traffic lights.

And it'll all be moved slightly to the south (into the Lorry Park) and made a bit bigger.

Workstarted in February and will then continue until August.

 

 

We are able to bring you the news of the development week by week to find out how things are going click on the links below

Following a slight delay in completing street lighting works, footway surfacing will now be

finished next week and all works are due to completed by Friday 27th August.

Week 28

All new street lighting columns are now installed and connected, and footway surfacing

will resume next using off-peak lane closures to finish the scheme along with signs,

bollards and the like. Works are due to be substantially finished by Friday 20th August.

 

 

The new traffic signals on the roundabout and at Hardwick Road were successfully commissioned this week and are now in use.

Fine tuning continues to ensure their timings are set to give the best performance for everyone using the roundabout.

Street lights are now being installed and pedestrian guard railing erected as the finishing

touches to Southgates roundabout continue

Southgates roundabout is nearing completion with works continuing on foot ways, street lights, signs and traffic signals

Works are nearing completion on the footways, street lights, signs and traffic signals. We thank you for your patience.
Works continue on finishing foot-ways, street lights, signs and traffic signals, with traffic signal poles now installed at the roundabout
and Nar Ouse Way.

Works continue on foot-ways, street lights, signs and traffic signals, with poles now evident

for the new pedestrian crossing in Hardwick Road:

The closure last weekend proved very successful, with nearly all the surfacing completed
plus a large part of the roadmarkings, and repairs to the Southgates Arch enabling the
roundabout to be reopened safely on Monday morning despite the burst water main on
Wisbech Road

 

Southgates roundabout in King’s Lynn will be closed from 6pm on Saturday 19th June to
6am on Monday 21st June for resurfacing.
Hardwick Road will be accessible from the Hardwick roundabout, but all traffic heading to
the town centre will be diverted via the A149 eastern bypass. Police, traffic wardens and
traffic management operatives will be on the diversion route to assist.

 

Week 19

Roadworks at Southgates roundabout in King’s Lynn continue to build up in preparation
for resurfacing works under the road closure on 19/21 June.

 

Week 18

Roadworks at Southgates roundabout in King’s Lynn continue to build up in preparation
for resurfacing works under the road closure on 19/21 June.
This week, traffic has been moved across onto newly widened areas to give room for new
islands to be built and for kerbing on the north side of the roundabout to be done.

Week 17

Roadworks at Southgates roundabout in King’s Lynn are now intensifying in preparation for resurfacing works under the road closure on 19/21 June

Week 16

Roadworks at Southgates roundabout in King’s Lynn are now about to enter a new phase.EDF connections on both high and low voltage diversions are nearly complete, so that old cables can be removed and road construction undertaken around the roundabout.

Week 15

Roadworks at Southgates roundabout in King’s Lynn are now in their fourth month. Completion of utilities diversion connections continues all around the roundabout.

Week 14

Roadworks at Southgates roundabout in King’s Lynn are now into their fourth month.Surfacing to widened sections of Hardwick Road and Nar OuseWay is well underway,and this photo taken from the top of the Southgates Arch gives an idea of how things are looking: Click here to see >>

Week 13

Roadworks at Southgates roundabout in King’s Lynn have now been running for three months. Nearly all drainage, cables, ducts and pipework beneath the ground have been laid, diversions of utility cables and pipes are nearing completion, new road formations are nearly done and now the first layers of surfacing are being laid on the widened Hardwick.

Week 12

Roadworks at Southgates roundabout in King’s Lynn continue slightly ahead of programme. Widening of Nar OuseWay continues with the wider turn intoWisbech Road

Week 11

Roadworks at Southgates roundabout in King’s Lynn continue to programme.Widening of Nar OuseWay is now becoming clearer with some new kerbs laid showing where the new road edge will be. Works are in hand to deal with the buried pipework from the old tar works which once stood here. No traffic control is needed for this section at present

Week 10

Roadworks at Southgates roundabout in King’s Lynn continue to programme.Road widening along the south side of Hardwick Road continues with some new kerbing now in place and the replacement electricity substation installed ready for connection.

Week 8

Roadworks at Southgates roundabout in King’s Lynn are maintaining very good progress. Advance planning and consultation for resurfacing and early commissioning of the traffic signals has started.

Week 7 

Roadworks at Southgates roundabout in King’s Lynn are now midway through their second month.

Works have begun to divert the water main along Hardwick Road, with initial connections done before the new main is laid.

Week 6

Roadworks at Southgates roundabout in King’s Lynn continue through their second month.

In the last week, major renewal of BT cables at Vancouver Avenue has been underway.These cables supply most of the town and their diversion is a key factor in completing road widening at the roundabout.

PDF created

Week 5

Roadworks at Southgates roundabout in King’s Lynn are now in their second month.

In the last week, new water main and BT ducts have been laid across Nar OuseWay and traffic signal ducts have been laid from Nar Ouse Way to the central island.

Week 4

Roadworks at Southgates roundabout in King’s Lynn have now been underway for a month, and significant progress has been made

Week 3

Works continue to progress well at Southgates roundabout in King’s Lynn.

New duct crossings have been finished in Hardwick Road and London Road, and the gas main diversion by Vancouver Avenue has started

Week 2

Works continue to programme at Southgates roundabout in King’s Lynn, having got off to a good start last week. Surfacing around the now smaller central island has allowed an extra lane for traffic to use while works continue around the junction. All splitter islands have now been broken out and reinstated with surfacing, and pedestrian refuges are being be formed using barriers to allow people to cross and give flexibility. Street lighting on the central island is now in use.

Week 1

Works have begun to improve Southgates roundabout at King’s Lynn. The official start date was Monday 1st February, but preparatory works began on the day before to help get the scheme off to a good start. This helped reduce traffic congestion on the Monday.

Works done in the first week include temporarily reducing the size of the central island by 3m to allow room for traffic as the works progress. This is due to be surfaced on Sunday. Street lights, bollards and signs on the splitter islands on all approach roads to the roundabout have been removed. The islands are now being broken out and reinstated with surfacing, and pedestrian refuges will be formed using barriers to allow people to cross and give flexibility. Temporary street lights have been fitted to the central island.

Southgates 1  
Southgates 2  

 
twitter

Sunday 05 February 2012

NOW PLAYING

Waiting for next track...

The Word on West Norfolk
12:00 to 14:00

Listen Now Listen Now

CALL 01553 692192 TEXT 07786 200 967 EMAIL >